WORK COMPLETED Rough grading efforts remain concentrated on the far northeastern portion of the site. Multiple access roads have been established, allowing for quick and efficient movement of equipment throughout the site. Additional labor has been on-site to maintain the silt fencing and waddles following the recent occurrences of heavy rain and high winds. Two…

WORK COMPLETED Grading efforts remain concentrated on the far northeastern portion of the site, where crews focus on some of the most variable topography on-site. Crews are performing rough grading, moving from the most northeastern portion of the site in the southwesterly direction. Final grades have been established and updated staking placed where applicable on…

WORK COMPLETED Three terraced groups of property, adjacent to the El Dorado Wash in the lower, northwestern portion of the site are approaching final grading efforts. A fourth, southeastern to the Cherry Tree extension, has also been significantly groomed for ease of future improvement, likely requiring additional fill. As final grades are established for these…

WORK COMPLETED Grading plan adjustments were made this week to improve lot and roadway elevations. Significant work is being conducted on and around the northeastern portion of the Villas property adjacent to El Dorado Wash northerly to the Cherry Tree Blvd. extension. Rough graded parcels are approaching completion at the western portion of the site….

WORK COMPLETED Clearing and grubbing began Monday June 26, 2017. Mass grading was initiated the following day beginning with residential lots in the southernmost cul-de-sac, to the northwest of Cherry Tree Blvd. Dirt was moved in the northeasterly direction to fill the southern edge of the El Dorado wash. Grading will continue northeasterly from this…