WORK COMPLETED Crews worked throughout the week to move the remains of the blasting on…
WORK COMPLETED Final grades have been received by the lower, Phase-1 lots. The southern commercial…
WORK COMPLETED This week final grades continued to be established on Phase-1 residential lots and…
WORK COMPLETED Throughout the week, efforts were primarily dedicated towards completion of the Phase 1…
WORK COMPLETED This week efforts transitioned heavily towards completion of the front commercial and residential…
WORK COMPLETED Following the completion of the uppermost parcels in the Villas last week, crews…
WORK COMPLETED Rough grading efforts remain concentrated on the far northeastern portion of the site….
WORK COMPLETED Grading efforts remain concentrated on the far northeastern portion of the site, where…
WORK COMPLETED Three terraced groups of property, adjacent to the El Dorado Wash in the…
WORK COMPLETED Grading plan adjustments were made this week to improve lot and roadway elevations….
WORK COMPLETED Clearing and grubbing began Monday June 26, 2017. Mass grading was initiated the…